Shaikh/ Jaber Al- Ahmad Al-Sabah Causeway project – Al Doha link
Commencement date: December 2014.
The project aims to link the country's south to its north to accommodate the increasing traffic density that is expected during the
next thirty years, and ensure the full flow of traffic towards Kuwait City, Shuwaikh Port, the port of Doha, Sheikh Jaber Al-
Ahmad Al-Sabah City, and Doha area.
The project consists of the construction of a road and a bridge linking the port of Shuwaikh area and semi Doha island through
John Sulaibikhat, in addition to connecting the existing roads in Doha and the intersection of Shuwaikh Port. The total length of
the Doha link is 12.4 km (Road highway at Doha area of 4.4 km long - cross-sea bridge through John Sulaibikhat of 7.7
kilometers long). The link has three lanes, with an emergency lane in each direction.
The cross-sea bridge contains navigational slots that has a width of 40 to 60 meters and a maximum height of up to 12 meters.
The bridge consists of three parts; the western bridge, the main bridge and the eastern bridge.
The project also includes three intersections:
First: The Amusement Park intersection: It’s a free intersection that connects Kuwait City, Jahraa, Shuwaikh Port, and Sheikh
/Jaber Al-Ahmed Al-Subah City, and so it ensures full flow of traffic in each direction.
Second: The Doha intersection: It is the second intersection when descending from the bridge in the Doha island to connect
with the highway road in Doha area.
Third: Shuwaikh Port intersection: It is the most important intersection in the project, as it fully connects with the main bridge
project, which makes it the link between the Subiya bridge’s link and the Doha bridge’s link.
The project also includes government buildings, which are:
Maintenance center and bridge management.
Control center and traffic control, which will be linked to the central system in Kuwait.
Truck weighing station in Doha area.
- Projects - The most important ongoing projects
Project data
Item
5.220 km
Approach bridge west ( marine )
1.305 km
Entertainment city interchange
Section Length
0.6 km
Main bridge ( marine )
1.785 km
Doha peninsula road
1.9 km
Approach bridge east ( marine )
1.620 km
Doha interchange
7.720 km
Off shore total
4.710 km
Onshore total
60,000 tons
Reinforcement
750,000 m²
Earthwork Filling
Major Quantity
640 nos
Bored Pile
360,000 m²
Concrete
150,000 m²
Contractor’s yard
total 369 nos
Precast units
others
Onshore Road
Offshore Bridge
Section plan and project Alignment