Location Supplies :

Box girders of casual launch of the bridge will be manufactured at the location of the project in Al-Sabiya. For this purpose, one

of the best precast concrete yard is established at a global level. The precast concrete yard is established In order to

manufacture box girders in a length of (40) m and (60) m, whereas the space of the casting yard is (268,800) cubic meters.

A floating crane will be used, its capacity is about (2,200) tons and its weight is about (80,000) tons. It is made especially to

compose(40) m and (60) m long box girders with. The space of the casting yard is (268,800) cubic meters. A Floating Crane of

a capacity of ( 2,200) tons and weight of (8,000) tons. It is made especially to compose (60) m box girders with giant ships that

handle transferring the burial generator to the location of the artificial islands. A horizontal launching girder will be used in this

operation. Its capacity is about (1,800) tons and its weight is (2,000) tons.

The number of the marine pieces that are used for the building process is approximately (80) pieces.

Stations of Manufacturing Concrete:

A temporary Iron bridge is built in Shuwaikh area (4) km long and the total weight is (14) thousand tons. It is built for the

purpose of successful termination of this major project.

Environment Preservation :

The Ministry of public works is using one of the best constructional technologies in order to protect the marine environment by

following the standards, systems and charts that are approved by Environment Public Authority. Also a complete environment

study is achieved under the observation of Environment Public Authority. Including establishing a project of complete

compensating coral reefs in the area and shrimp and marine living creature’s habitat. In addition to building these habitants for

the living creatures and to transferring them to their new habitat.

In which the marine living creatures are observed in order to make sure of their adaptation with the new environment. The

observation operation shall be under a program which is managed by the Environment Public Authority. Also by using

surveying system by diving periodically to observe any changes and to make sure of availability of the living creatures.

An information system is available to manage the environment data (EDMIS) in this project .The information system works

through the available observation environment data and a constant contact with the concerned authorities. Whereas the

reports should be submitted to the Environment Public Authority to be reviewed periodically and to set recommendations about

it.

General statistics of the project :

(36.14) km (the marine bridge 27.5 km, the

land bridge 8.6 km).

Total Length

Total traffic lanes (6), the required speed is

(120) km per hour and 2 safety sides.

Road

(1,052) pieces of precast concrete launch.

The Upper

Structure

(1,526) molded columns at the site.

Foundations