A brief about the project
Project name
Location: Al Jahra governorate.
Development and maintenance of Alabdali road
between Mutla'a city exit in the most south intersection
(1) and the suggested intersection (5) 26.2km length.
Improve Al-Abdely road from the future Mutla’a city to
the intersection with the northern regional road.
Location: Al Jahra governorate.
Development and maintenance of Alabdali road
between intersection (5) and Al-Abdely borders 41.5km
length.
Improve Al-Abdely road from the future intersection
with the northern regional road to Al-Abdely borders.
Location: Hawalli governorate – South Surra area.
Aim to solve expected traffic congestion problem when
the projects being implemented in that area end.
Construct, complete and maintenance roads, bridges
and other services in South Surra including the
intersections from Damascus street and King Faisal.
Location: Hawalli governorate – South Surra area.
Aim to solve expected traffic congestion problem when
the projects being implemented in that area end.
Construct, complete and maintenance roads, bridges
and other services in South Surra including
intersections from 5
th
ring road to King Fahad road.
The project extend for 22km from the 6th ring road at
Al-Salmi road direction and meet intersection 82 with
the regional road south part and Al-Abdali linked road
(east – west) to connect the north & the south of
Kuwait.
Construct, complete and maintenance the northern
regional road from 6
th
ring road to intersection no (4).
The project extend for 23km at Al-Salmi road direction
and meet intersection 58 with the extension of the 7th
road, the project involves 4 intersections and parking
and rest house.
Construct, complete and maintenance the northern
regional road from intersection (4) to intersection (8).
The project extend for 56km to the Saudi Arabia
kingdom border entry, the project involves 5
intersections and parking and rest house.
Construct, complete and maintenance the northern
regional road from intersection (8) to Al-Salmy Entry.
Total length approximately 6.5 km.
Construct and maintenance Al-Ghous street from 5th
ring road to 6th ring road.
Total length approximately 9 km.
Construct and maintenance Al-Ghous street from
Sabah Al-Salem area to 7
th
ring road.
Total length approximately 10 km.
Construct and maintenance Al-Ghous street from 7
th
ring road to Al-Fahaheel road Al-Ahmadi no (212).
Location: Kuwait city (the capital).
Infrastructure of roads, storm water drainage, sewage
and other utilities.
Construct, complete and maintenance roads and
rainwater drainage sewers and other services east Al-
Sulaibikhat.
Location: Al Jahra governorate.
Construction of asphalt road 27.5km length two ways
with (3 lanes) and (4) bridges plus lighting works, storm
water drainage and other civil works.
Construct and design roads and other services to
execute the new road from Al-Subiya road to Buhaith
Gate.
Follow / A statement about the Roads future projects in the final design stage
الباب الأول
–
المشاريع
Chapter 1 - Projects
الدليل الإحصائي السنوي
Statistical Year Book
155
3-
أهم المشاريع المستقبلية
The most important
Future projects