Chapter 1 - Projects

Second:

Project: Developing Jamal Abdul Nasser Street

Starting date: May 2011.

Completion date until September 2014 : 40.96%.

The Ministry of Public Works is responsible for the Jamal Abdul Nasser road development project, which includes the

conversion of the current road to a multi-storey highway that features global highways standards which in return will

become one of the largest international infrastructure projects in the region. The project aims to raise the absorptive

capacity of the road’s capacity and upgrade the level of security and traffic safety, leading to a reduction of accidents

rates and reduce traffic congestion significantly, and is considered one of the strategic projects implemented by the

Ministry in preparation for the requirements of future traffic and raise the level of services to road users.

The project is located in the western side of Kuwait (Al-Asema). It runs from Al-Jahra Gate’s roundabout (Sheraton

Roundabout) until Eastern Ghirnata area, north of Al-Asema. The project is considered to be the infrastructure of many

government, educational, and health agencies and bodies such as Kuwait University, General Authority for Applied

Education and Training, major hospitals that are located in the region adjacent to the road, in addition to the Kuwait

Ports Foundation, which will contribute to the facilitation of access and departure movements from and into those

mentioned places through the separation of different traffic paths, both crossing and local.

Project Stages:

Due to the nature of the region and the high rate of traffic flow, the implementation works has been split into five

phases, which are all being worked on at the same time in order to avoid traffic congestion at peak times, facilitate the

movement of entry and exit to and from all regions and existing services on both sides the road. The five phases of the

project are as follows:

First stage:

Starts from First Ring Road (Al-Salam palace), and ends at the

Airport road.

Second stage:

Starts from Al-Sabah hospital’s roundabout and ends at Girnata

area, towards Al-Sulaibikhat area.

Third stage:

Starts from Al-Razi hospital’s intersection and ends at the Gazali

road’s intersection.

Fourth stage:

Starts from the Airport road and ends at the Gazali road.

Fifth stage:

At the Gazali intersection only.

الدليل الإحصائي السنوي

Statistical Year Book

101

2-

أهم المشاريع الجارية

The most important

Ongoing projects