الباب الأول
–
المشاريع
Chapter 1 - Projects
First
:
Project: the connected road between the Custodian of
the Two Holy Mosques road and Fahaheel Expressway:
Completion date: June 2014.
Location: Al Ahmadi Governorate
.
Second:
Project: roads and other services in the coastline area
(stage 2):
Completion date: June 2014
Project location: Mubarak Al Kabeer governorate.
Third:
Project: roads and services in South Subahiya area
(Stage 4) :
Completion date: May 2013
Location: Mubarak Al Kabeer governorate
4
Total road length
3
Total number of lanes
3
Number of interchanges
71
Number of light columns
1.510
sanitation
Lengths of
utility
services
0.719
drainage of rain water
2.1
telephones
21
Total road length
782
Number of light columns
7.3244
sanitation
Lengths of
utility
services
7.543
drainage of rain water
0.403
electricity
7.4563
telephones
2.7204
water
الدليل الإحصائي السنوي
Statistical Year Book
67
1-
الإنجازات
Achievements
From the Ministry of Public Works’ accomplished projects in the field of infrastructure, residential
areas and internal roads development, which aim to develop and improve the infrastructure services
such as roads, sanitation and nutrition of fresh water, irrigation and drainage of rain water,
electricity, telephones, and lighting systems.