Introduction to SE-100
 
1. Investigation, Study and Design
  • Study Report including Topographical survey, Geo-technical Survey Existing utilities, Effluent flow details analysis.
  • Environmental Impact Assessment Study & report
  • Value Engineering Study & Report
  • Project Management Plan
  • Preliminary Design Report with drawing, Calculations & Specifications.
  • Draft Final Design Report with drawing, Calculations & Specifications.
  • Final Design Report with drawing, Calculations, Specifications & BOQ
2. Construction of Pumping Station at Jahra STP site
  • Administration and Service Building 3 floors
  • Deep depth Pump Station Building with basement floors
  • Electrical Sub-Station / Generator Building.
  • Guard house
  • Site Development works
  • Access Roads & Street Lighting
  • Water Supply, Drainage, storm water and Process piping
  • Site communication & Electrical cabling
  • Equipments & Pumps works
  • Electrical, Telephone, Fire Alarm, CCTV & Security system works
  • ICM & Telemetry works
  • HVAC, Plumbing, Fire fighting system works
3. Construction of KUBD Sewage Treatment Plant.
  • Non Process Buildings
    Administration building
    Workshop building
    Laboratory building
    Sub-station Buildings and D.G. building
    Guard Houses
  • Process Structures
    Inlet works building
    U.V. System building
    Chlorination building
    Wash water/Irrigation Pump Station
    Thickener & Dewatering building
    Disk filter
    Aerobic digester building
  • Site Development works
    Access Roads & Street Lighting
    Water Supply, Drainage, storm water and Process piping
    Site communication & Electrical cabling
  • Process & Storage Tank Structures
  • Process Equipments works
  • Distribution chambers / inflow structure.
  • Landscaping & Irrigation system works.
  • Electrical, Telephone, Public Addresses, CCTV & Security system works
  • ICM & Telemetry, Fire Alarm works
  • HVAC, Plumbing, Fire fighting system works
4. Construct two Transfer Pipe lines from Jahra Pumping station to Kubd WWTP including chambers.
5. Construct Effluent Transfer Lines from newly constructed Kubd WWTP to Reservoirs at DMC including chambers.
6. Construct overflow line from Kubd WWTP connecting to Sulaibiya Overflow lines including chambers.
7. Construct overflow lines from Jahra Pumping Station connecting to existing Jahra WWTP overflow line including chambers.
8. Construct Septic Tank waste Reception system at Kubd WWTP up to quantity 3000m³/day complete with proper building, road and emptying points for tankers with suitable odour control facilities.
9. After completion of new system, disconnect & demolish the existing Jahra Treatment Plant.
10. Conversion of existing 1100mm pumped TSE line from existing JAHRA WWTP to DMC into a gravity line from DMC to the new Irrigation pump station at Jahra Pump Station site.
11. Construct to connect birds sanctuary from the TSE line from DMC.
12. Design and construct a new irrigation pumping station at new Jahra Pumping station.
13. Lay fiber optics cables with all lines interconnecting Jahra Pumping Station to Kubd WWTP, from Kubd WWTP to DMC and from DMC to Jahra Pumping Station.
14. 11KV double circuit Cables and overhead lines from Sulaibiya WWTP substation to Kubd WWTP Substation including O/H line towers.
15. Operation and Maintenance for the constructed facilities.
 
         
 
 